Work is about to start in Ashgrove and Enoggera on the final stage of the SEQ Water Grid: Ashgrove to Enoggera Pipeline Upgrade.

This stage of the upgrade involves taking a two kilometre pipeline along Wardell Street – between Frasers Road and Pickering Street – out of service.

Work will involve removing valves, fittings and connections under the road at various points along the existing old water pipeline.

Work will be conducted at the intersections of Wardell Street and:

  • Frasers Road
  • Dovedale Crescent
  • Stark Street
  • Banks Street
  • Lloyd Street
  • Samford Road.

Work will start in late-March 2017 and take about six weeks in total to complete, subject to weather and other unexpected delays. To minimise traffic disruptions, working hours will be between 6pm and 5am, Monday to Friday.

You will be notified if interruptions to your local water supply are expected at any time.

For more information, email watergrid@seqwater.com.au or call 1800 427 799.