In September–December 2017, Seqwater will be conducting maintenance on the Mt Crosby Weir Bridge between Stumers Road and Allawah Road.

The work will involve repairs to the downstream toe of the weir, installing two new sluice gates to manage water releases and strengthening the guardrails on either side of the bridge.

Work will take about three months to complete, subject to weather conditions and other unexpected delays. Standard working hours will be between 7am and 5.30pm, Monday to Friday.  Some Saturday work may be required at times.

Traffic management will be in place when required. If you are in the area, please look out for signage, follow the instructions of our workers and do not pass any barricades we have erected for your safety.

Signage will be in place notifying motorists in advance of any bridge closures.

For more information, contact the Seqwater Community Relations team via email communications@seqwater.com.au or call 1800 771 497.