In June 2018, Seqwater will be shutting down the Mt Crosby East Bank Water Treatment Plant for essential maintenance and asset condition assessments.

The shutdown will allow us to conduct activities including the replacement of ten large valves and design investigations for the future upgrade of the treatment filters at the plant.

To reduce the time the treatment plant is offline, work will be conducted 24 hours a day for about three days during the shutdown period, subject to unexpected delays.

Equipment will include cranes, excavators, pumps and trucks. Neighbours may notice an increase in noise, lights and traffic, but we will work to minimise disruptions where possible.

The work is not expected to interrupt water supply.

For more information about this work, email communications@seqwater.com.au or call the Seqwater Community Relations team on 1800 771 497.