Lake Macdonald Dam Improvement Project
Seqwater is upgrading Noosa’s Lake Macdonald (Six Mile Creek) Dam as part of its Dam Improvement Program. Early works are underway.
About the project
Across Queensland and Australia, there are multiple dam upgrades occurring to meet modern engineering standards.
Seqwater’s Dam Improvement Program is ensuring its dams comply with the latest safety standards and continue to function safely during extreme weather events in line with regulatory requirements.
The Lake Macdonald Dam Improvement Project will include constructing a temporary upstream cofferdam, a new spillway and reconstructing the existing earth embankments.
We are proud to be partnered with John Holland as the major construction contractor for this essential project.
The enhancements will not only improve water supply reliability but also bolster the dam’s ability to manage extreme weather conditions, ensuring regulatory compliance now and in the future.
Early site establishment began in November 2024, with main construction activities scheduled to commence in 2025. The project is anticipated to take around five years to complete, depending on weather and site conditions.
Project update
Early site establishment began in November 2024, with main construction activities scheduled to start in 2025.
The entire construction process, from building the cofferdam to its removal after the new dam wall is complete, is anticipated to take around five years, depending on weather and site conditions. Key activities will include:
- Vibratory piling
- Concrete and rock breaking
- Earthworks
- Concrete pours
- Rock filling.
Please note that the construction schedule is subject to change based on environmental and operational factors.
Approved working hours are:
- Monday to Friday: 6:30 AM – 6:30 PM
- Saturday: 6:30 AM – 4:00 PM
Due to the nature of the construction, certain activities will take place outside these hours. We will notify nearby residents in advance of any such work and will outline the specific activities, expected duration and any measures in place to mitigate impacts.
Early works
Early works for site establishment commenced early November 2024, in preparation for main construction works in 2025. Site establishment includes construction of office buildings, car parking spaces, haul roads, pipe work, a construction laydown area and minor vegetation removal. For more information on the works, view the early works notification here.
An Early Works Environmental Management Plan (EWEMP) has been prepared to ensure that the environmental and social effects are effectively managed, monitored and reported during the works. You can view a copy of the EWEMP here.
Design
This image shows the new split level spillway layout, including the upper labyrinth spillway (zigzag portion of the dam wall), and the new embankment.
The design for the new dam wall at Lake Macdonald is a split-level concrete spillway. The primary 'lower ogee' spillway is set at the original lake level, and an upper labyrinth spillway for higher floods.
A labyrinth spillway is an overflow weir, zigzag in shape which creates a longer total effective length over the spillway to enable higher flows caused by large rain events. The labyrinth spillway provides an efficient means of increasing spillway capacity without raising the dam’s crest.
The earth embankments will be reconstructed to their original level on either side of the spillway.
Scour protection will be an addition, with rocks placed downstream of the spillway to prevent erosion.
An outlet tower will be constructed to the left side of the spillway which will have mechanical pipework and electrical components to facilitate both emergency release of water, to lower the dam reservoir, and environmental flows to the downstream Six Mile Creek.
At completion of the project, the new dam will have the same storage volume and full supply level as the existing dam (storage to 8,000ML).
Project scope
The Lake Macdonald Dam Improvement Project will include:
- Lowering of the Lake Macdonald water storage to accommodate construction. Seqwater has worked to minimise this impact, with a temporary water level that will be reduced by approximately two metres, from the full supply level (technically speaking this will be at RL 93m or 42%). This water level will provide water security reliability for the Noosa community and maintain access to the lake and local ambience.
- Relocation of fish by expert fish biologists, via a purpose-built fish transport vehicle, to Cooloolabin Dam.
- Construction of a cofferdam to protect the site and manage flows in Six Mile Creek during construction.
- Demolition of the existing spillway and dam wall.
- Removal of unsuitable foundation material under the new spillway, excavating down to a rock foundation, then backfilling with mass concrete.
- Construction of a split-level concrete spillway. The primary spillway will be set at the original lake level, and an upper labyrinth spillway will be constructed for large floods.
- Removal and reconstruction of the earth embankments on either side of the primary spillway.
- Ground improvement works below the new embankments.
- Provision of a new outlet works structure to enable environmental releases downstream of the dam into Six Mile Creek.
Additional works include fish protection measures (including proposed construction of a fishway at Gympie Weir), land management activities and rehabilitation.
Upstream cofferdam
A cofferdam structure will be built to undertake the construction work safely. A cofferdam is an enclosure built within a body of water to allow the enclosed area to be pumped out or drained. The pumping creates a dry working environment so that the dam wall construction work can be carried out safely.
The cofferdam for the Lake Macdonald Dam Improvement Project will be:
- 300 metres long
- 10 metres wide
- Approximately the same height as the current dam wall.
This is a temporary measure for dam safety during construction and once the new dam wall is complete, the cofferdam will be removed, and the dam will naturally refill to its original full supply level.
Lake lowering
Seqwater has worked to minimise environmental impacts from this project, with a revised construction methodology that will temporarily reduce the water level by approximately 2 metres, from the full supply level.
Technically speaking, Lake Macdonald will sit at about 42 per cent of its full supply level (or 93 metres).
This reduced water level will allow the construction work to safely take place. The lake will remain at this level throughout construction unless dry conditions create a naturally lower level.
The Noosa Water Treatment Plant will continue to be operated as per the annual operating strategy and the monthly operational supply schedule (currently 20ML/d on average).
Community Reference Group
In 2024, the Lake Macdonald Dam Improvement Project re-established the Community Reference Group (CRG).
The purpose of the Lake Macdonald Dam Improvement Project CRG is to provide a formal channel for community input on issues of relevance and highlight any local concerns that may relate to the project. The group will also assist in the dissemination of information about the project throughout the region.
The meeting notes and presentation will be published below, following each CRG meeting:
- Meeting 1:
- Presentation, Tuesday 3 December 2024
- Meeting notes, Tuesday 3 December 2024 – tbc
- Animation of construction process
For more information
If you have any questions about the project, please see the project FAQs below, or get in contact with the project team.
Phone us: 07 5472 1565
Email the team: [email protected]
Stay informed as this project progresses, by signing up to project updates below.
We invite you to attend our community information sessions to learn more about the project and share your thoughts:
- 11:30am-2pm, Tuesday 28 January - Cooroy Library, 9 Maple St Cooroy
- 10am-12:30pm, Saturday 1 February - Cooroy Memorial Hall, 23 Maple St Cooroy
- 2:30-5pm, Wednesday 5 February - Cooroy Library, 9 Maple St Cooroy
- 9-11:30am, Saturday 15 February - Pomona Memorial Hall, 6 Reserve St Pomona
- Project updates
- FAQs
- Resources
-
Community Newsletter – January 2025
20 Jan 2025
This newsletter provides the latest project information on Jan-Feb 2025 community events, the construction schedule and construction impacts. To read the newsletter, click here.
Project Update Community Newsletter - December 2024
19 Dec 2024
This newsletter provides the latest project information and project updates for the months of October-December 2024 as well as a look ahead to major construction in 2025. To read the newsletter, click here.
Invitation for submissions - Project change applications – Construction
16 Dec 2024
The Lake Macdonald Dam Improvement Project team submitted a project change application to the Coordinator-General relating to proposed changes to the temporary cofferdam design for water security reasons.
The Coordinator-General is inviting the community to make a submission on the proposed changes to the project.
The application is available online at Six Mile Creek Dam Safety Upgrade project | State Development, Infrastructure and Planning.
Submissions open on Monday 16 December 2024 and will close on Tuesday 28 January 2025.
To make a submission, please visit:
- Online: https://haveyoursay.dsd.qld.gov.au
- Email: [email protected]
- Post: Attention: The Coordinator-General
c/- Project Manager - Six Mile Creek Dam Safety Upgrade Project
Office of the Coordinator-General
PO Box 15517
City East Qld 4002 Australia
Lake Macdonald Dam Improvement Project Community Reference Group - Expressions of interest now open
4 Nov 2024
Seqwater is inviting expressions of interest from the community to participate in the reformed Lake Macdonald Dam Improvement Project Community Reference Group (CRG).
The purpose of the Lake Macdonald Dam Improvement Project CRG is to provide a formal channel for community input on issues of relevance and highlight any local concerns that may relate to the project. The group will also assist in the dissemination of information about the project throughout the region.
The Lake Macdonald Dam Improvement Project CRG will:
- Provide input to ongoing project planning to ensure both community and Seqwater needs are represented, project impacts are understood and addressed, where possible, and any opportunities and benefits are considered and maximised.
- Assist in refining the potential social impacts of the project and possible mitigation measures by confirming or updating information provided by the former CRG in 2019.
- Actively involve the community and key stakeholders in planning to ensure the project delivery meets community expectations, including for the proposed coffer dam.
- Raise awareness and understanding of the project in the community through the active sharing of information between well informed CRG members and their local networks.
- Improve Seqwater’s understanding of community impacts and concerns related to the project.
We’re seeking applications and looking for a variety of community members such as those who live near the dam, live upstream or downstream of the dam, local businesses, and/or have a heritage or environmental interest. Being on the CRG is a voluntary, unpaid position, and will require a commitment of some personal time.
To learn more about the CRG and selection criteria, read the Terms of Reference and the Selection Criteria.
Nominations will be open for a two-week period from Monday 4 November 2024 to Sunday 17 November 2024.
The first Community Reference Group meeting will be held local to Lake Macdonald Dam on Tuesday 3 December from 3:30pm – 5:30pm. It is expected that the successful applicants will be available to attend the meeting in person on this date. Information on the meeting location will be provided to successful applicants.
To apply to be a Lake Macdonald Dam Improvement Project CRG member, complete the application below or email [email protected].
Lake Macdonald DIP | Community Newsletter | August 2024
1 Aug 2024
Seqwater’s Lake Macdonald Dam Improvement Project is progressing, with detailed planning and onsite works continuing in 2024. Read the August community newsletter for the latest updates.
Geotechnical investigation works underway on Lake Macdonald Dam Improvement Project
30 Jul 2024
Seqwater’s Lake Macdonald Dam Improvement Project is progressing, with geotechnical investigations underway.
Part of Seqwater’s Dam Improvement Program, the Lake Macdonald Dam Improvement Project will ensure the dam continues to operate safely into the future and provide water security for years to come.
Seqwater awarded the construction contract to John Holland Queensland in February 2024, and the geotechnical investigations will confirm the requirements for the project’s temporary cofferdam, which will deliver several benefits to the local community and environment throughout construction.
Planning and site preparation works will continue in 2024 and include survey works, water quality testing, installation of project fencing, and continued engagement with the community and traditional owners.
Seqwater’s Interim CEO, Will Harpham, said Seqwater is committed to the delivery of this critical project to ensure this important water source continues to serve the Sunshine Coast community now and into the future.
“Part of Seqwater’s Dam Improvement Program, the Lake Macdonald Dam Improvement Project will ensure the dam meets modern engineering standards, continues to operate safely during extreme weather events, and provides water security for generations to come,” Mr Harpham said.
“While Lake Macdonald Dam continues to operate safely, dam design and engineering standards, along with knowledge of weather and flood risks, have evolved since the dam was originally constructed in 1965, so this upgrade is about ensuring the longevity of the dam into the future,” he said.
The project involves building a new split-level concrete spillway and upper labyrinth and reconstructing the existing earth embankments.
The project temporary works design, which was released by Seqwater earlier this year, includes the installation of an upstream cofferdam to keep the lake water level as high as possible for water security, the environment, some recreation activities, and community amenity throughout construction.
Seqwater is working through the construction methodology based on the design, and major works, including the installation of a temporary cofferdam, are expected to commence in 2025 after this year’s wet season.
The Lake Macdonald Dam Improvement Project is expected to support approximately 150 jobs over the life of the project, and Seqwater is committed to keeping the community informed as this important project progresses.
John Holland awarded Lake Macdonald Dam Improvement Project construction contract
20 Feb 2024
Seqwater has awarded John Holland the construction contract for the upgrade of Noosa’s Lake Macdonald (Six Mile Creek) Dam.
Part of Seqwater’s Dam Improvement Program, the upgrade will enhance water security and enable the dam to withstand extreme weather events.
The project involves building a new split-level concrete spillway and upper labyrinth and reconstructing the existing earth embankments.
Major site construction activities will commence later in the year.
Community info sessions begin for Lake Macdonald Dam Improvement Project
12 Feb 2024
Seqwater has released the final design concept for the upgrade of Noosa’s Lake Macdonald (Six Mile Creek) Dam, with early works commencing ahead of major construction in mid-2024.
Part of Seqwater’s Dam Improvement Program, the upgrade will enhance water security and enable the dam to withstand extreme weather events.
Seqwater is committed to keeping the community informed throughout the project and will hold community information drop-in sessions in February and March, where the project team will be available to talk through the design and construction approach and answer any questions.Community Information Drop-In Sessions:
Cooroy Memorial Hall:
• Tuesday 13 February: 2:30pm – 5:00pm, Cooroy Memorial Hall
• Monday 19 February: 9:30am – 12:00noon, Cooroy Memorial Hall
• Tuesday 19 March: 2:30pm – 5:00pm, Cooroy Memorial Hall
Pomona Memorial Hall:
• Saturday 2 March: 9:30am – 12noon, Pomona Memorial Hall
Early works begin on Noosa’s Lake Macdonald Dam Improvement Project
10 Jan 2024
- Early works on the Lake Macdonald Dam Improvement Project have commenced, ahead of major construction mid-2024
- Creating 150 jobs for Sunshine Coast locals
- New split-level concrete spillway to increase the dam’s capacity to withstand extreme weather events, and maintain water security
Seqwater has released the final design concept for the upgrade of Noosa’s Lake Macdonald (Six Mile Creek) Dam, with early works commencing ahead of major construction in mid-2024.
Part of Seqwater’s Dam Improvement Program, this upgrade will enhance water security and enable the dam to withstand a 1 in 500,000-year flood event.
The dam improvement project involves building a new split-level concrete spillway and upper labyrinth and reconstructing the existing earth embankments.
Following a comprehensive technical review undertaken in 2021 and 2022, the new optimised design will increase the dam’s capacity to withstand extreme weather events while also ensuring the dam remains operational during construction for water security and some recreation activities.
Seqwater has worked hard to keep the lake water level as high as possible during construction. The lake will be temporarily lowered for construction work to occur safely, and a temporary cofferdam will be installed to support water security during construction. The Noosa Water Treatment Plant will continue to operate during construction.
This will be the first major upgrade of Lake Macdonald Dam since its original construction in 1965. Importantly, more than 150 local jobs are expected to be created over the life of the project.
Survey works are currently underway on-site, with site establishment and lake lowering occurring over the coming months. Major work to construct the temporary cofferdam is expected to commence mid-2024, following contractor appointment.
Due to the significant nature of the project, some recreational use of the lake and surrounding areas will be disrupted during construction. However, recreation activities at Lake Macdonald, Lake Macdonald Park and the Noosa Botanic Gardens will remain open.
Seqwater will keep the community informed throughout the project and will hold information sessions early-2024 where the project team will be available to talk through the design and construction approach and answer any questions.
Quotes attributable to Minister for Water, Glenn Butcher:
“I’m pleased to see progress on this critical project. This important upgrade will ensure the longevity of Lake Macdonald Dam so it can continue to provide water security and dam safety for years to come.
“Dams in Queensland are built to very high, internationally accepted safety standards, but methods used to estimate extreme weather and flood risks have changed significantly since some were built.
“This is one of several important dam safety projects being undertaken by Seqwater. Since 2015, Kinchant Dam, Eungella Dam, Wappa Dam, Boondooma Dam, Leslie Harrison Dam, Fairbairn Dam, and Sideling Creek Dam (Lake Kurwongbah) have been completed across Queensland.
“With construction starting soon, the upgrade is also set to boost local employment opportunities in the region, with around 150 jobs expected to be created over the life of the project.”
Quotes attributable to Seqwater CEO, Neil Brennan:
“While Lake Macdonald Dam continues to operate safely, the upgrade will ensure the dam meets updated engineering and safety standards, taking into account extremely rare weather scenarios and climate change.
“The revised design will allow water to be retained in Lake Macdonald during construction, some recreation activities to remain open, reduced impact on aquatic life, plants and animals in and around the lake, and will ensure the Noosa Water Treatment Plant continues to operate for local water supply.
“Projects of this scale are complex and require significant planning time and we thank the community for their understanding while we undertook this important work.”
Further Information:
Through its Dam Improvement Program, Seqwater is investing in South East Queensland’s dams to ensure they provide water security for years to come.
Dams are long-life assets which require continual assessment, monitoring and maintenance.
Seqwater’s dam infrastructure upgrades are progressively being delivered and are due for completion by 2035.
Seqwater undertakes regular monitoring and engineering assessment to make sure the region’s dams continue to operate safely.
Lake Macdonald Dam Improvement Project Update
10 Jan 2024
Throughout 2021 and 2022, Seqwater worked with a Technical Review Panel to evaluate and short-list options for the Lake Macdonald Dam Improvement Project.
In 2023, Seqwater worked to confirm the preferred design option and obtain the required state and federal approvals to proceed with the project.
Seqwater has completed comprehensive engineering, environmental and economic studies; as well as taken on the feedback from the previously established community reference group in 2019. All of this information has gone into informing the best design approach that focuses on reducing potential project impacts to the community and environment.
Seqwater finalised the design option in late 2023 which involves a new split-level concrete spillway, with an upper labyrinth spillway for extreme floods (see design section for detail).
While this is an important project to ensure the ongoing safety of the structure during extreme weather events, Seqwater is committed to avoiding or reducing the impacts of construction wherever possible.
Areas of impact assessed included, but were not limited to, water security and the lake level, traffic, noise, dust, water quality, recreation, cultural heritage, and ecology. Seqwater has also taken onboard community feedback obtained through the previous Community Reference Group sessions, where possible.
Project planning has included the modification of the construction methodology, and there will now be:
- The use of a coffer dam, to retain water throughout the project
- More water in Lake Macdonald during construction
- The Water Treatment Plant will continue to operate, utilising water from the lake
- Environmental flows will be maintained as per the condition of the water license
- Reduced impact/risk to aquatic life, plants and animals in and around the lake
- Recreation areas at Lake Macdonald Park will remain open during construction:
- The boat ramp at Lake Macdonald Park, next to the Noosa Botanic Gardens
- Fishing, stand up paddle boarding, canoeing
- Benefits to local community and visitors by keeping the lake open
- The project will employ local contractors and procure local businesses where possible.
-
No FAQs match your query
What is the Dam Improvement Program (DIP)?South East Queensland dams were built to high safety standards, but most were built some decades ago. Methodologies and data used to estimate extreme rainfall events continue to improve and industry engineering standards and understanding of risks can progress over time.
Across Queensland and Australia, there are multiple dam upgrades occurring to meet modern engineering standards.
Seqwater’s Dam Improvement Program is ensuring the region’s dams comply with the latest safety standards and continue to function safely during extreme weather events in line with regulatory requirements.
Click here for more information on Seqwater’s DIP, including dam upgrades which have been delivered and currently under planning.
Why does Lake Macdonald Dam need to be upgraded?Lake Macdonald – also known as Six Mile Creek Dam – was originally constructed in 1965.
There have been significant advances in dam design since the dam was built, as well as new ways of estimating extreme rainfall and flood events, and a greater understanding of the size and severity of earthquakes.
This will be the first major upgrade of the dam since the wall was raised in 1980. The Lake Macdonald Dam Improvement Project will:
• increase the spillway capacity to safely pass floods
• protect the dam wall in extreme flood events
• efficiently control water flowing out of the dam
• reduce risks to the dam structure during earthquakes
• meet modern design and engineering standards
• comply with dam safety guidelines.What will Lake Macdonald Dam look like following the upgrade?The new dam will occupy the same footprint as the current structure, however the spillway will be a split-level concrete spillway. The primary ‘ogee’ spillway is set at the original lake level, and an upper labyrinth spillway will be constructed for large floods. No spillway gates are included in the new structure and the earth embankments will be reconstructed to their original level on either side of the primary spillway.
The primary spillway is a flat concrete structure, similar to the current dam wall.
The labyrinth spillway has a zigzag shape when viewed from above and is made from concrete. In the event of a very large inflow, the water will flow over the upper labyrinth spillway and into Six Mile Creek downstream.
The current earth fill embankment on the Lake Macdonald Drive side of the spillway does not meet today’s design and safety standards – that is, it is too steep and at risk of erosion. The new embankment at this location will be the same size and height of the existing embankment and finished grass and rocks.
The right earth embankment on the other side of the dam's spillway, closest to the water treatment plant, will also be re-constructed and finished with grass (looking much the same as it does now).
Rocks will be placed downstream of the new spillway, called scour protection, and will assist in preventing erosion.
An outlet tower will be constructed to the left side of the spillway which will have mechanical pipework and electrical components to facilitate both emergency release of water, to lower the dam reservoir, and environmental flows to the downstream Six Mile Creek.
When will main works begin and what will they involve?Construction works are planned to begin from March 2025, subject to approvals and environment conditions. Works will take place between 6:30am and 6:30pm Monday to Friday, weather and construction conditions permitting. Working hours on Saturday are between 6:30am and 4:00pm, as needed.
The entire construction process, from building the cofferdam to its removal after the new dam wall is complete, is anticipated to take around five years, depending on weather and site conditions.
Key activities will include:
- Vibratory piling
- Concrete and rock breaking
- Earthworks
- Concrete pours
- Rock filling.
Please note that the construction schedule is subject to change based on environmental and operational factors.
How long will the dam upgrade take?Construction of the Lake Macdonald Dam Improvement Project (DIP) will be delivered in four (4) phases and is expected to be completed in 2029, subject to weather and construction conditions.
Construction phases and timeframes are as follows:
- Phase 1 (2025) – Construction of temporary cofferdam
- Phase 2 (2025-2026) – Demolition of existing dam wall
- Phase 3 (2026-2028) – Construction of new dam wall and infrastructure
- Phase 4 (2028-2029) – Remove cofferdam and site rehabilitation.
How much will this project cost?The Lake Macdonald Dam Improvement Project is a $427.7 million project to ensure ongoing dam safety and water security for years to come.
Will construction impact water security for the region?To maintain local water security during the construction of the project, a minimum Full Supply Volume of 42% will be retained for Lake Macdonald Dam (which equates to a level of 93m AHD), and the Noosa Water Treatment Plant will continue to operate.
To the community, this will look approximately two metres lower than the dam's full supply level.
This is the level the lake will remain throughout construction unless dry conditions create a naturally lower level.
Does the need for this project mean the dam is currently unsafe?All Seqwater dams within the Dam Improvement Program continue to operate safely. Dam improvements are undertaken to meet modern guidelines for these life-long assets – many of which were built some years ago.
Seqwater undertakes regular monitoring and engineering assessments to ensure all our dams continue to operate safely.
Dams in Queensland were built to high, internationally accepted safety standards. However, the methodologies and data used to estimate extreme weather events and flooding impacts have significantly improved, and engineering standards and risks have progressed.
All these factors are considered as part of Seqwater’s Dam Improvement Program so our dams continue to operate as they should, now and into the future.
What will the cofferdam look like?A 300 metre long, 10 metre wide temporary cofferdam structure is engineered to manage inflows after each rain event. This structure will hold back the water in Lake Macdonald during construction of the new dam wall.
This is a temporary measure for dam safety and once the new dam wall is complete, the cofferdam will be removed, and Lake Macdonald Dam will be able to naturally refill to its original full supply level.
What materials will the cofferdam be constructed from and how will it be built?The cofferdam will be constructed from sheet piles, tie-bars, structural steel members, rock bags, and graded rock fill. Cranes equipped with vibratory and impact hammers will drive the sheet piles into place. The same cranes will be used to install the tie-bars, structural members, and rock bags. Rock fill will be delivered by trucks and positioned using earth-moving equipment.
What impacts can be expected during construction and mitigation measures will be in place?The community can expect to see an increase in standard construction impacts intermittently throughout the project including noise, dust, vibration and increased heavy vehicle movements.
At times, out of hours work including weekend, night and continuous work will be required to complete time critical activities.
We will provide advance notification to the community and stakeholders prior to commencing any out of hours works.
We understand some activities will be more disruptive for residents in close proximity to the project, and will be in contact with those directly affected to advise of impacts and mitigation measures in advance.
Click to read our fact sheets for more information on traffic management, work hours, and noise, dust and vibration mitigation measures.
We thank the community in advance for your patience and understanding while these essential works are carried out.
What impacts will there be to recreation areas?Lake Macdonald is expected to remain open to on-water recreation, and parks and facilities recreation throughout the project. This means Lake Macdonald, Lake Macdonald Park and the boat ramp along Lake Macdonald Drive will remain open, as well as the Noosa Botanic Gardens. Recreation activities including motorless boating, canoeing and fishing will be permitted outside of the construction zone, which the cofferdam will isolate.
There will be closures to the scouts campground, the Mary River Cod Park and boat ramp, the fishing platform on Lake Macdonald Drive and some walking, riding and horse trails.
The Noosa Trail Network will remain open, however access points to the trails may change during construction. Vehicle parking and foot access will be closed at the Lake Macdonald Drive trail head (near Kookaburra Park) and along Collwood Road due to construction activities. Plans to provide alternative access and vehicle parking for the Noosa Trails Network in this vicinity are being worked through with Noosa Shire Council.
What will traffic impacts be?During construction, the local community and stakeholders will see an increase in construction traffic, including heavy vehicles in and around Lake Macdonald.
Heavy vehicles are approved by the Office of the Coordinator-General to use Elm Street and Lake Macdonald Drive, and these will be the main areas with increased construction traffic.
A Traffic Management Plan has been developed to ensure the safety of residents, road users and construction workers during the project.
Temporary traffic changes will occur at different times and may include speed limit reductions, lane closures, temporary traffic signals, traffic controllers on site and temporary signage.
Fencing and barriers will also be installed to delineate safe work areas from public spaces.
We will provide advanced notifications to the community and stakeholders prior to any major traffic changes or diversions.
Will there be any roads close during construction?During construction there may be partial road closures and temporary changes to traffic conditions at times for the safety of road users.
We will provide advance notification of any road closures, including details of any detours.
How will impacts to the natural flora and fauna be mitigated?We are working with qualified ecologists to ensure the well-being of local flora and fauna, implementing measures to protect and manage wildlife during construction.
To date, Seqwater and John Holland have undertaken extensive environmental investigations to identify and record plant and animal habitats in and around Lake Macdonald.
The investigations include field surveys focusing on protected plants, important habitats for plants and animals, aquatic environments and significant local species. It also included reviewing past and present reports and databases.
Click here for more information on ecological management and mitigation measures.
Will there be fish relocation in the lead up to construction?Investigations are underway into the measures needed to manage aquatic fauna at the 42% or 93m reduced water level. Seqwater will develop a recovery and relocation plan, in consultation with key stakeholders, to manage any aquatic fauna impacted during the lowering and throughout construction.
It is expected there will be a period when the habitat available for aquatic species, including those of conservation significance such as the Mary River cod, Australian lungfish, Mary River turtle, white-throated snapping turtle, and platypus, is limited. To minimise the impacts to these important species, Seqwater is proposing an initial aquatic fauna relocation program.
We will aim to relocate species of conservation significance before construction begins. Some fish are sensitive to handling or changes in water temperature and may suffer injury or mortality if relocated. Therefore, appropriate measures will need to be identified and incorporated into the management approach.
All relocation will be delivered by expert fish biologists, via a purpose-built fish transport vehicle to Cooloolabin Dam.
Will a fish ladder be included in the upgrade?There is no existing fish passage (a fish ladder is a specific type of fish passage) at Lake Macdonald Dam, and no proposed fish passage included in the Lake Macdonald Dam Improvement Project. The reasons for this are:
- A fish passage could allow for pest species such as Tilapia to enter Lake Macdonald reservoir.
- A more suitable location for a fish passage has been identified at the Gympie Weir. A fish passage in this location will allow fish to pass up and down the main Mary River, allowing passage between the upper tributaries and reaches.
- The Coordinator-General, as part of the Project Approval Conditions, has stated that Seqwater upgrade the Gympie Weir to include a fish passage.
-
Video
LAKE MACDONALD ANIMATION
FileLake Macdonald DIP fact sheet - noise
FileLake Macdonald DIP fact sheet - flora and fauna
FileLake Macdonald DIP fact sheet - traffic management
FileLake Macdonald DIP fact sheet - work hours
FileLake Macdonald DIP community update - August 2024
FileLake Macdonald Community Engagement Summary Report - May 2024
VideoMaking controlled water releases from dams and pipelines
VideoSeqwater explains: six stages of a dam safety upgrade
VideoUnderstanding the SEQ Water Grid